Discussion about this post

User's avatar
Brian Gowthorpe's avatar

The sunk cost is enormous, as you say, but it does seem likely that, following approval, the project was moved into detailed design and procurement, which are much more expensive. The long history of this controversial project doubtless also carries costs stretching back decades as successive governments wrestled with objections and revised proposals. The heritage issues require a sensitive solution, hence the objections, but taking France’s high speed rail lines and road schemes as nearby examples, the French government seems to take a much more command and control approach. This is partly cultural, but also reflects demographic differences. Worldometer suggests that England (not the UK where the effect is diluted) is at least 3.5 times more densely populated than France.

Gareth Huw Davies Writer's avatar

I Thanks for throwing light on that £179m. But t's very likely that work on building the tunnel and associated dual carriageway leading to and from it, well within the wider world heritage site, would be well underway by now, and probably too well advanced for Labour to axe it, even in July 2024, had it not been for Stonehenge Alliance’s campaign.

The Alliance successfully used the UK courts to delay and eventually help scupper the works.

In 2021 the High Court quashed the initial 2020 approval. When the government then re-approved the plan in July 2023, the Alliance launched a second judicial review. Although the High Court dismissed this challenge in February 2024, the Alliance appealed against the decision, keeping the project in legal limbo, Rachel Reeves was then able to cancel a scheme that hadn't even started, that £179m notwithstanding.

1 more comment...

No posts

Ready for more?